Maharashtra cancels Rs 998 crore deal to Kalpataru Power

11 Jun 2009 Evaluate

The Maharashtra Government has decided to cancel a Rs 998 crore contract awarded to Kalpataru Power Transmission (KPTL), under Phase-II of the feeder separation programme, on the grounds of substandard work. The Maharashtra Power Minister, Mr Sunil Tatkare, made the announcement in the State Assembly on Tuesday and added that an enquiry would be conducted.

 

According to the calling attention notice tabled in the State Assembly, Phase-I of the programme began in 23 districts in June 2006 for setting up 897 feeders with a provision of Rs 943 crore. KPTL was given a Rs 388-crore contract to set up 751 feeders. The State imposed a Rs 99.50-lakh fine on the company for the Phase-I delay. Despite this, the Phase-II contract was awarded to KPTL as its rates were low.

 

Phase-II kicked off in October 2007 in 20 districts in which KPTL was given a Rs 998-crore contract to set up 955 feeders. The notice said KPTL was way behind schedule in January 2009 and had put up only 190 feeders so far.

 

The village feeder separation programme is being implemented by the Maharashtra State Electricity Distribution Company to manage power supply in rural areas. The plan is to create separate power feeders for agriculture and domestic power consumption so that load shedding can be managed effectively and people in the rural areas face fewer problems.

crackcrack

Kalpataru Projects Share Price

1282.25 9.15 (0.72%)
01-Nov-2024 18:59 View Price Chart
Peers
Company Name CMP
Larsen & Toubro 3626.30
Rail Vikas Nigam 470.80
NCC 312.50
KEC International 1001.70
Kalpataru Projects 1282.25
View more..
© 2024 The Alchemists Ark Pvt. Ltd. All rights reserved. MoneyWorks4Me ® is a registered trademark of The Alchemists Ark Pvt.Ltd.