Jayant Infratech has bagged its biggest ever work order till date which is worth Rs 54.24 crore from ECI-SEEIPL(JV) for the Supply, Erection Testing and Commissioning of 25 kV, 50 Hz, Single Phase, Traction Overhead Equipment, Traction Substation, Switching Station and other associated works from chainage (-) 1.214 to chainage 105.000 & WCL siding, Chord line, Loop lines, bridges etc in connection with railway Electrification Work between Naghbir to Itwari section in Nagpur Division of South East Central Railway. This contract is executable over in 300 days.
Jayant Infratech is engaged in the field of Railway Infrastructure Development involving design, drawing, supply, Erection and Commissioning of 25KV, 50Hz Single Phase Traction Overhead Equipment.